EXECUTIVE INSIGHTS | 10 min read | 25 Mar 2026

SAFe without ITIL is the natural starting point for an organisation in transformation, but heavy ITIL processes can smother agility before it gains traction. ITIL without SAFe is the trap large software vendors fall into: everything is controlled, and nothing ships fast enough to matter.

Reality sits in between, in a blind spot that rarely gets documented: the three-party trap between client, vendor and system integrator, where each party turns the others' leverage against the organisation. The French would call it a ménage à trois, and the client always picks up the bill. Sprints run in circles, story points become artificial, and the Change Advisory Board (CAB) turns into the bottleneck where projects die of administrative suffocation.

This article draws on my time as project director at a large French automotive parts manufacturer. It gives you three operational keys to:

  • keep control of your contract and of the value your ERP is supposed to deliver;
  • stop governance from becoming an obstacle to timely delivery;
  • refuse invoices inflated by artificial complexity.

SAFe and ITIL in an ERP project: two distinct roles, not two options

SAFe (Scaled Agile Framework) is a framework for delivering at scale. Teams work in a cadence of Planning Intervals (PIs), typically 8 to 12 weeks long (SAFe 6.0 renamed the former Program Increment). Each PI delivers working increments, provided dependencies can be planned: visible, stable and resolvable within the cadence.

ITIL is a framework for managing IT services in production. Its change enablement practice decides what goes live, independently of the development team's rhythm. ITIL 4 calls whoever authorises a change the change authority; for high-risk changes, that is often a CAB.

These are not alternatives. They cover two distinct scopes: SAFe governs the Build (creating), ITIL governs the Run (stabilising). Mixing them without a clear contractual boundary creates exactly the conditions for gridlock.

The three-party trap: why three parties produce one loser

On a Teamcenter–SAP integration project with a partial cloud migration, the three parties had structurally incompatible agendas.

The software vendor runs its own version roadmap and controls access to the technical specifications of its connectors. Not out of bad faith: it is a competitive advantage built into its business model. The more integrations run through its native tools, the longer the client relationship lasts, and ecosystem partners have every reason to recommend the vendor's own middleware. Each recommendation consolidates technical dependencies, and contracts.

The system integrator, often contracted for Application Management Services (AMS, what French contracts call TMA, tierce maintenance applicative), is paid on billable hours. Its incentive is not speed but complexity. Broad user stories, partial specifications and unresolved dependencies all justify high estimates, and a change request on every ticket left waiting.

The client is caught in between, with no contractual lever on the vendor's specifications or on the integrator's pace. It pays for motion, not results.

The Aikido effect. In Aikido, you neutralise an opponent by redirecting their own force. Here, each party does exactly that, against the client. The vendor imposes an upgrade; the integrator turns it into a billing event. The integrator creates complexity; the vendor covers it with technical opacity. The client absorbs both, with no enforceable recourse against either.

Key #1: define the contract before choosing the method

The first mistake is choosing SAFe or ITIL before defining the contractual scopes. A method cannot make up for missing governance. It makes things worse by giving that absence an appearance of rigour.

Three scopes must be separated in the contract before signing, never after the first deadlock.

Vendor support covers incidents, security patches and version upgrades. Every commitment needs enforceable response times and documented conditions for access to technical specifications, particularly for third-party connectors and integration interfaces. This scope belongs to ITIL, not SAFe, and must never enter a sprint backlog.

Evolutionary AMS covers custom developments and new integrations. This is where SAFe applies, provided user stories can be specified independently of the vendor's roadmap. The definition of "done" must be contractually enforceable: a story cannot be declared delivered if its validation depends on an interface that is not yet stable.

The integration project covers delivery milestones and, critically, vendor dependencies written into the contract: response times for specification requests, upgrade conditions, connector access. Without this framework, a vendor upgrade in the middle of the project triggers a global deadlock.

Key #2: understand why Agile fails without control of the code

SAFe, like every Agile method, rests on a prerequisite that is rarely spelled out: teams must be able to specify what they are going to build. That means access to interfaces, data schemas and business rules, enough to break a requirement down into user stories with verifiable acceptance criteria.

In a multi-vendor ERP project, that condition is not guaranteed. A connector, the software component that lets two systems exchange data (here, Teamcenter and SAP), is technically an interface: a data exchange contract with its own rules, formats and constraints. It can take several forms. A REST API is the most common today: system A sends a request, system B returns the data. A SOAP service is an older standard, still widespread in legacy SAP and Teamcenter environments. SAP also uses its own IDocs (intermediate documents), structured formats for exchanges between modules and third-party systems. Each comes with its own structure, authentication and versioning rules.

When the vendor controls these specifications and shares them only partly with the integrator, nobody can estimate accurately what nobody can specify. A user story then becomes an envelope of billable hours, not a delivery commitment. The effects on Agile mechanics are direct:

  • the backlog is no longer controlled by the project team; the vendor's release of technical information partly dictates it;
  • the definition of "done" becomes unenforceable, because validation depends on an interface whose specifications may change with the next version;
  • velocity measures activity, not value: sprints close, burn-down charts look healthy, and nothing reaches production.

Running SAFe when neither the client nor the integrator controls the technical scope is like measuring progress on a building site where nobody holds the blueprints. The method is sound. The context does not meet its prerequisites.

The answer is not to abandon SAFe. It is to restrict it to the scope where those prerequisites are met, and to write access to specifications into the contract before the first sprint.

Key #3: configure the CAB to protect, not to block

On this project, the CAB handled two very different kinds of change in the same way: a security patch, low risk and mandatory, which should have gone through within 48 hours, and a custom module deployment, high risk, which needs a full review with integration testing. In the same queue, critical patches waited for weeks. Meanwhile, the integrator billed each waiting ticket as a change request.

The dysfunction had an architectural cause. Customisations had been built into the application core instead of sitting on a stable extension layer, so every change touched the same components and the CAB could not tell them apart in practice.

This is where architecture and governance meet. A customisation patched into the core creates a dependency neither SAFe nor ITIL can absorb. SAFe cannot plan a backlog whose specifications change with every vendor release. ITIL cannot separate a security patch from a custom deployment if both touch the same components. Architecture decides whether the Build/Run separation can be governed at all. Assess it before signing, not at the first upgrade.

ITIL 4 already provides the tools. It distinguishes standard, normal and emergency changes: a standard change is low-risk, well understood and pre-authorised, so it does not wait for the board. A properly configured CAB therefore runs at least two tracks: a fast track for low-risk, limited-impact changes, and a full review for high-impact or wide-scope changes. That split belongs in the vendor support contract, not in the hands of a committee convened in crisis mode.

Already under contract? Don't miss the renegotiation window

All of this works best before signing. In practice, many CIOs read it already committed: an AMS contract running, vendor support in place, an integration project started without this separation. Three opportunities remain.

Contract renewal is the main renegotiation window. A renewal is the moment to reset scopes, introduce differentiated service levels and require documented access to interface specifications. Do not let a tacit renewal carry the same flaws forward.

Timeline synchronisation is routinely underestimated. If your AMS contract renews in June and the vendor has an upgrade planned for September, the window closes in June, not after the upgrade. Mapping the key dates of every contract and every vendor roadmap lets you anticipate friction instead of absorbing it each cycle.

A documented incident is leverage too. A recorded deadlock, such as an upgrade that froze the project or a critical patch stuck in the CAB queue for weeks, is a concrete argument for renegotiation. Record impacts, delays and costs systematically.

If you cannot act before signing, act at the next contractual window. If that window is not yet visible, start by mapping it.

What this means for your ERP programme

Is your multi-vendor ERP programme being governed, or endured?

If your sprints produce activity without results in production, if your CAB holds critical patches in the same queue as custom deployments, or if your integrators bill for waiting rather than progress, the problem is neither SAFe nor ITIL. It is the missing contractual separation between Build and Run, which should have been set before the programme started. The wider market context is covered in the analysis of the industrial ERP software landscape in France, and the strategic stakes of vendor dependency in the digital deficit and your ERP strategy.

In the RESONANCE™ method, this Build/Run separation is set during the scoping phase: mapping vendor dependencies, structuring the three contractual scopes, and configuring the CAB by risk level. Each party then has a clear scope, measurable deliverables, and governance that serves the client rather than the vendor ecosystem. The consulting services page describes how these engagements run.

These friction points are predictable. The free assessment helps you spot them and write them into your contracts before they turn into billable deadlocks.

Assess your ERP governance

Sources

Sources consulted for this article, list updated in November 2026.

Field experience
  • Project director assignment, PLM/ERP integration programme, French automotive parts manufacturer (unpublished field experience)
Frameworks and vendors
Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Marketing
Set of techniques which have for object the commercial strategy and in particular the market study.
Quantcast
Accept
Decline
Unknown
Unknown
Accept
Decline
Analytics
Tools used to analyze the data to measure the effectiveness of a website and to understand how it works.
Google Analytics
Accept
Decline
Advertisement
If you accept, the ads on the page will be adapted to your preferences.
Google Ad
Accept
Decline
Save